Lunar Apartments
Works have been progressing very well on the apartment building. The structure has now risen above ground as the builder is currently forming up Level 2, and they aim to top-out the structure by the end of this summer.
Upcoming works at lower levels will include stripping the formwork to the basement and commencing on the installation of building services.
At this stage construction works for the Apartments are scheduled to be complete by the end of September 2020.
Lunar Townhouses
Lunar Townhouses were unfortunately delayed due to the extensive civil and infrastructure works running through site. Inclement weather, existing site conditions and design challenges hindered the civil contractor, delaying hand over of the site to the builder.
Fortunately, the builder has now been working on the Townhouses for the past four months and has been spending time on foundations, in-ground hydraulics, procuring materials and finalising the letting of remaining trades.
Wall frames are ready for delivery and will be installed over the coming two months, with roof and window installation soon following. After reviewing the program with the builder, construction of the Townhouses is now scheduled to be complete by the end of November 2020.
Eclipse Townhouses
Stage 1 & 2
All deep level civil and infrastructure works are now complete. The builder has been progressing well with individual plumbing works for the first eight Townhouses. The foundations will be poured over the coming months and wall frames will be erected after this.
The trades will continue works in this order progressing between the various stages. After reviewing the program with the builder, construction of the Townhouses are now scheduled to be complete by mid-December 2020.
Eclipse Heritage Apartments
Works on the Eclipse Heritage Apartments commenced this year. The building has been opened up and all ground floor windows and doors have been removed.
Additional foundations are set to be installed along with temporary propping, before select internal demolition occurs. Construction works for the Heritage Apartments are scheduled to be complete by mid-December 2020.
Eclipse Townhouses
Stage 3
Throughout the end of 2019 and into the new year, Fortunato Group carried out all Eclipse Townhouses bulk civil works and deep infrastructure works, which are now complete.
We are 90% through finalising the Building Contract and will be providing you with some exciting news notifying you of the builder soon.
Design development is commencing imminently, and we are working towards achieving a building permit over the coming months.
After reviewing the program with the builder, construction of the Townhouses are scheduled to start mid-April with an anticipated 12 month build duration.